How long does it take to design a project and to build it?

It depends on three things, and none of them is the installation work. The first is how long the client takes to decide the scope, which is the one that varies most and the one nobody puts in the schedule. The second is the building work and coordination with the other trades: the cable cannot be pulled until the routes are there, and the ceilings cannot be closed until the cable is in. And the third is the supply of the equipment, which has stopped being a constant and is confirmed when quoting, not when ordering.

That is why we give the schedule in phases and with the dependencies written down: what has to be done, by the client and by the building works, for each phase to be able to start. An overall schedule with no dependencies is a number that is missed in the first month, and from then on nobody knows whose the delay is.

What does not get compressed is commissioning and testing. When the building works run late, the temptation is to cut exactly there, because it is the last thing and it does not show. It is precisely the part that cannot be cut.

All the questions.

Five hundred and forty-four, grouped by topic. Each with its own page.

Get started

See it working.

A written answer is enough to decide whether it interests you. To know whether it works at your site you have to see it on a real scene, with the image as it is and, on top of it, what the system understands from it. That is on the IRIS Neural website, which is the group's product.